Sr. No. |
Name of Work |
Actual Date of Start/ Time period |
Stipulated Date of completion |
1 |
Construction of 1 DSP residence,18 Type-II and 18 Type-III Houses in CID Colony Patel Nagar Hisar. |
11.03.2019 |
05.09.2020 |
2 |
Special Repair of One Superintendent, 4 Deputy Superintendent and 26 Warder Staff Houses & Boundary Wall in Central Jail-II at Hisar. |
11.06.2019 |
8.09.2020 |
3 |
Up-gradation of 7 DSP Residences in New Police Lines, Hisar. |
03.09.2019 |
17.08.2020 |
4 |
Construction of Vehicle Parking shed in Govt. College at Hisar. |
13.09.2019 |
4.08.2020 |
5 |
Construction of Administrative Block at Govt. College for Women, Hisar. |
13.09.2019 |
27.07.2020 |
6 |
Construction of Assistant Director Residence (FSL) at Hisar. |
13.09.2019 |
10.04.2020 |
7 |
Construction of Mtrakaksh in City Police Station Hansi, Sadar Police Station Hansi and Police Station Narnaund at Police Distt. Hansi. |
19.11.2019 |
16.07.2020 |
8 |
Construction of Mtrakaksh in Police Station Barwala and UklanaDistt. Hisar. |
29.11.2019 |
25.09.2020 |
9 |
Construction of Mtrakaksh in Sadar Police Station and Civil Lines in Distt. Hisar. |
29.11.2019 |
27.05.2020 |
10 |
Construction of Mtrakaksh in Police Station Agroha and AdampurDistt. Hisar. |
29.11.2019 |
15.08.2020 |
11 |
Construction of Police Station Bass in Police Lines, HansiDistt. Hisar. |
17.12.2019 |
15.05.2021 |
12 |
Construction of 22 Class room &Vechile Parking in Govt. College at Hisar. |
06.03.2020 |
2.10.2021 |
13 |
Up-gradation of Office and Branches of SP Hisar. |
06.03.2020 |
01.11.2020 |
14 |
Up-gradation of Forensic Science Laboratory in Police Lines, Hisar. |
09.03.2020 |
05.09.2020 |
15 |
Construction of Multipurpose Shed in Govt. P.G College at Hisar |
09.03.2020 |
06.08.2020 |
16 |
Up-gradation of DAV Police Public School, Hisar. |
19.03.2020 |
17.09.2020 |
17 |
Additional Work for Govt.College at UklanaDistt.Hisar |
24.06.2020 |
20.03.2021 |